We’re just awarding a R&M contract, the successful contractor is challenging us on the fluctuations clause in the contract. They want either:
1) A fixed 7% year on year increase for the duration of the contract (3+2), or
2) Annual increases in line with CPI, but no decreases.

I wondered if anyone in this group had recently awarded a contract and could share what the fluctuation arrangements were?